Project description
- Canalisation at Rossmarktplatz in Solothurn
- Renovation of an oval pipeline 600 / 900
- Length 15 m1
- Using Vandex Uni-Mortar + concrete sludge
Implementation 2013
Total construction sum CHF 22,000
Project description
Implementation 2013
Total construction sum CHF 22,000
Building owner and construction management
Architekturbüro Daniel Bieri
Fallernweg 2
4515 Oberdorf
Reference: Daniel Bieri
Telephone: 032/ 623 85 05
Contractor$
Weiss+Appetito AG
Building Reconstruction
Bielstrasse 109
PF 540
4503 Solothurn
Telephone: 032 621 14 15
Key personnel
Techn. management: Andreas Bischof
Site manager: Beat Rawyler
Foreman: Ricardo Castroman